Due to large scale of Gomishan shrimp farm, its impacts on the environment and environmental sensitivity in the study area, it is required to implement project in compliance with environmental standards. Therefore, it is essential to construct retention pond in the outlet of the drainage channel. Initial studies indicate that wastewater of shrimp farm is the most important factor affecting the environment and on the other hand, Gomishan wetland is the most sensitive environmental areas, which will be the main receptor of wastewater.

Actual services:

The following construction activities have been done in the project, in which, Asarab was responsible for performing superior and construction supervision on them;

  • Excavation at a depth of about 1.5 meters in an area of 20 hectares
  • Creating a dike with clay in a layer of 15 cm depth with a density of 95%
  • Transferring, deposition and profiling of surplus soils around the pond